Construction Projects
Manistee City Hall · Home, KS · 4 days ago
ManagementTemporary
Construction updates for the week of July 20, 2026.
River Street Streetscape
This Past Week
- Backfill excavation area for retaining wall
- Sidewalk repairs and resetting existing brick pavers
- Completed installation of pipe bollard bases at Oak Street
- Started installation of new storm sewer
- Started installation of underground electrical conduits
- Continued brick paver installation in the Plaza
Next Week
- Continue placing brick pavers in Plaza, working west to east
- Continue installation of storm sewer
- Continue installation of underground electric
- Start concrete work in the intersection of River and Oak Streets
Current Traffic Control
- Detour route is set up on Maple Street to Water Street
- Oak Street intersection will have limited access during construction and will be closed at times
- Access to all businesses is open in the work zone and closed section of River Street
- Temporary walkway has been installed for access on the south side of River Street, east and west of Oak Street
Fountain Park
This Past Week
- Began removal and stripping of topsoil
- Fountain was removed and shipped out for refurbishing, returning to Manistee later this year
Next Week
- Remove fountain basin and foundation
- Complete miscellaneous removal items
Veteran’s Memorial Park Improvements
This Past Week
- Amphitheater area is still open and has access for use
- Last load of retaining wall block delivered
- Started on framing repair on west fishing deck
- Grading for retaining walls is ongoing
- Installation of modular concrete retaining walls continues, and some areas have been completed
- Additional framing work for wood decks continued
Next Week
- Continue the preparation work for the retaining walls
- Continue installing modular concrete retaining wall
- Continue to repair wood framework on the boardwalk
Riley Apartments (Manistee Township)
This Past Week
- Connected water main to the City’s system if all testing passes
- Connected the Bus Barn water service to new main
Next Week
- Details not specified
2026 Street Improvements
Planned to start on August 4th. Molon plans on starting with milling and paving on Division B at First Street and Division C at Seventh Street.
The Project Includes Three Divisions
Division A - 14th Street, Maywood Avenue, and 15th Street Improvements
- Full road reconstruction of 14th Street, Maywood Avenue, and 15th Street from Care Center Drive to Vine Street
- Project consists of drainage swales, machine grading, upgrading permanent signing, HMA paving, and minimal concrete work
Division B - 1st Street and Maple Street Rehabilitation
- HMA cold milling and resurfacing of Maple Street from 12th Street to Memorial Drive (excluding the Maple Street Bridge)
- HMA cold milling and resurfacing of First Street from Maple Street to Cypress Street (US-31)
- Upgrading permanent street name signs from S. Lakeshore Drive to Maple Street
Division C - 2026 Miscellaneous City Street Overlays
- Butt joint milling, structure adjustments, and HMA overlaying of miscellaneous City streets